Extremely challenging site location and logistics for unitised glazing
Extremely challenging programme dates
Gaining Permission for road closures on Red Route
The Brief
Working with the architect at planning stage, Bespoke Glass Structures submitted a pc sum to the client for the required works. We were appointed to the project and worked with the architect to come up with some provisional designs.
Our Approach
Programme and methodology were vital to the whole approach and were the major drivers throughout the design process.
After completion of deign with the architects we run this through with our structural engineer to complete all calculations ensuring everything designed was fit for purpose.
A detailed methodology was worked through with the main contractor tendering for the scheme, in view of avoiding a full scaffold wrap to the building and using an alternative approach to save costs.
Architectural cladding and metalwork were also included in our package.
The Result
Now fully complete, the project looks highly impressive and have made the clients & Architects vision a reality.
The Frameless glazing allows natural light to flood the building enhancing the offices experience. With the right preparation, planning and design; we were able to achieve perfection.